Dept. of Trans. PROGRESS Serial No. Contract No. 07-144-10-53 02-381604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 9% 02-LAS-395-30.7/56.7 Federal Project: ACST-P395(215) PH-P395(215) Progress payment No. 02 Payment period ending: 05-18-07 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,164,592.50 1,819,613.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -34,245.86 4. Earned Subject to Retention 2,164,592.50 1,785,367.64 5. Mobilization 1,286,114.10 1,286,114.10 6. Total Work Completed 3,450,706.60 7. Deductions -3,000.00 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,447,706.60 3,068,481.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,068,481.74