Dept. of Trans. PROGRESS Serial No. Contract No. 07-236-11-49 02-381604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 28% 02-LAS-395-30.7/56.7 Federal Project: ACST-P395(215) PH-P395(215) Progress payment No. 05 Payment period ending: 08-20-07 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,147,439.20 2,522,095.18 2.a. Extra Work 56,339.50 0.00 b. Adjustment Comp. -295,620.00 -295,620.00 3. Materials on Hand 4. Earned Subject to Retention 10,908,158.70 2,226,475.18 5. Mobilization 2,443,616.79 0.00 6. Total Work Completed 13,351,775.49 7. Deductions -24,000.00 -7,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,327,775.49 2,219,475.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,219,475.18