Dept. of Trans. PROGRESS Serial No. Contract No. 07-269-13-46 02-381604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 38% 02-LAS-395-30.7/56.7 Federal Project: ACST-P395(215) PH-P395(215) Progress payment No. 06 Payment period ending: 09-20-07 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,210,941.23 4,063,502.03 2.a. Extra Work 56,339.50 0.00 b. Adjustment Comp. -295,620.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 14,971,660.73 4,063,502.03 5. Mobilization 2,572,228.20 128,611.41 6. Total Work Completed 17,543,888.93 7. Deductions -24,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,519,888.93 4,192,113.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,192,113.44