Dept. of Trans. PROGRESS Serial No. Contract No. 07-297-20-32 02-381604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 44% 02-LAS-395-30.7/56.7 Federal Project: ACST-P395(215) PH-P395(215) Progress payment No. 07 Payment period ending: 10-19-07 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,680,041.63 469,100.40 2.a. Extra Work 213,812.73 157,473.23 b. Adjustment Comp. -173,027.27 122,592.73 3. Materials on Hand 4. Earned Subject to Retention 15,720,827.09 749,166.36 5. Mobilization 2,572,228.20 0.00 6. Total Work Completed 18,293,055.29 7. Deductions -34,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,259,055.29 739,166.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 739,166.36