Dept. of Trans. PROGRESS Serial No. Contract No. 07-332-16-23 02-381604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 51% 02-LAS-395-30.7/56.7 Federal Project: ACST-P395(215) PH-P395(215) Progress payment No. 08 Payment period ending: 11-20-07 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,238,773.88 2,558,732.25 2.a. Extra Work 215,624.33 1,811.60 b. Adjustment Comp. -173,027.27 0.00 3. Materials on Hand 4. Earned Subject to Retention 18,281,370.94 2,560,543.85 5. Mobilization 2,572,228.20 0.00 6. Total Work Completed 20,853,599.14 7. Deductions -44,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,809,599.14 2,550,543.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,550,543.85