Dept. of Trans. PROGRESS Serial No. Contract No. 08-053-15-42 02-381604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 54% 02-LAS-395-30.7/56.7 Federal Project: ACST-P395(215) PH-P395(215) Progress payment No. 11 Payment period ending: 02-20-08 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,785,491.61 35,479.44 2.a. Extra Work 308,889.40 0.00 b. Adjustment Comp. 189,001.86 0.00 3. Materials on Hand 4. Earned Subject to Retention 19,283,382.87 35,479.44 5. Mobilization 2,572,228.20 0.00 6. Total Work Completed 21,855,611.07 7. Deductions -2,000.00 44,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,853,611.07 79,479.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 79,479.44