Dept. of Trans. PROGRESS Serial No. Contract No. 08-238-08-02 02-381604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 90% 02-LAS-395-30.7/56.7 Federal Project: ACST-P395(215) PH-P395(215) Progress payment No. 18 Payment period ending: 08-20-08 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,534,129.66 124,840.00 2.a. Extra Work 594,573.88 18,386.03 b. Adjustment Comp. 1,473,083.76 -53,432.58 3. Materials on Hand 4. Earned Subject to Retention 28,601,787.30 89,793.45 5. Mobilization 2,572,228.20 0.00 6. Total Work Completed 31,174,015.50 7. Deductions -16,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 31,158,015.50 89,793.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 89,793.45