Dept. of Trans. PROGRESS Serial No. Contract No. 06-331-10-39 02-387304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 43% 02-SHA-5-58.0/67.0 Federal Project: ACIM-005-8(325) ACIM-005-8(325) Progress payment No. 04 Payment period ending: 11-20-06 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,675,427.54 189,094.07 2.a. Extra Work 31,204.22 0.00 b. Adjustment Comp. -3,785.06 -1,223.22 3. Materials on Hand 4. Earned Subject to Retention 1,702,846.70 187,870.85 5. Mobilization 689,440.50 229,813.50 6. Total Work Completed 2,392,287.20 7. Deductions -1,580.57 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,390,706.63 417,684.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 417,684.35