Dept. of Trans. PROGRESS Serial No. Contract No. 06-355-15-30 02-387304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 54% 02-SHA-5-58.0/67.0 Federal Project: ACIM-005-8(325) ACIM-005-8(325) Progress payment No. 05 Payment period ending: 12-20-06 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,036,807.49 361,379.95 2.a. Extra Work 187,976.22 156,772.00 b. Adjustment Comp. -3,785.06 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,220,998.65 518,151.95 5. Mobilization 689,440.50 0.00 6. Total Work Completed 2,910,439.15 7. Deductions -1,580.57 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,908,858.58 518,151.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 518,151.95