Dept. of Trans. PROGRESS Serial No. Contract No. 07-171-15-00 02-387304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 58% 02-SHA-5-58.0/67.0 Federal Project: ACIM-005-8(325) ACIM-005-8(325) Progress payment No. 09 Payment period ending: 06-15-07 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,914,254.84 3,223,737.12 2.a. Extra Work 223,638.77 0.00 b. Adjustment Comp. -5,102.11 0.00 3. Materials on Hand 4. Earned Subject to Retention 8,132,791.50 3,223,737.12 5. Mobilization 873,291.30 0.00 6. Total Work Completed 9,006,082.80 7. Deductions -9,580.57 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,996,502.23 3,222,737.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,222,737.12