Dept. of Trans. PROGRESS Serial No. Contract No. 07-206-13-32 02-387304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 64% 02-SHA-5-58.0/67.0 Federal Project: ACIM-005-8(325) ACIM-005-8(325) Progress payment No. 10 Payment period ending: 07-20-07 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,808,164.79 2,893,909.95 2.a. Extra Work 270,170.01 46,531.24 b. Adjustment Comp. -16,739.18 -11,637.07 3. Materials on Hand 4. Earned Subject to Retention 11,061,595.62 2,928,804.12 5. Mobilization 919,254.00 45,962.70 6. Total Work Completed 11,980,849.62 7. Deductions -12,580.57 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,968,269.05 2,971,766.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,971,766.82