Dept. of Trans. PROGRESS Serial No. Contract No. 07-269-14-17 02-387304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 92% 02-SHA-5-58.0/67.0 Federal Project: ACIM-005-8(325) ACIM-005-8(325) Progress payment No. 12 Payment period ending: 09-20-07 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,823,132.81 482,953.02 2.a. Extra Work 513,624.68 107,047.33 b. Adjustment Comp. -24,355.92 0.00 3. Materials on Hand 4. Earned Subject to Retention 15,312,401.57 590,000.35 5. Mobilization 919,254.00 0.00 6. Total Work Completed 16,231,655.57 7. Deductions -12,723.07 6,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,218,932.50 596,000.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 596,000.35