Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 07-318-13-39 02-387304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 89% 02-SHA-5-58.0/67.0 Federal Project: ACIM-005-8(325) ACIM-005-8(325) Progress payment No. 14 Payment period ending: 10-19-07 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,977,610.73 0.00 2.a. Extra Work 878,098.92 319,031.56 b. Adjustment Comp. -24,355.92 0.00 3. Materials on Hand 4. Earned Subject to Retention 15,831,353.73 319,031.56 5. Mobilization 919,254.00 0.00 6. Total Work Completed 16,750,607.73 7. Deductions -17,723.07 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,732,884.66 319,031.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 319,031.56