Dept. of Trans. PROGRESS Serial No. Contract No. 07-356-17-52 02-387304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 100% 02-SHA-5-58.0/67.0 Federal Project: ACIM-005-8(325) ACIM-005-8(325) Progress payment No. 16 Payment period ending: 12-20-07 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,223,307.92 50,839.71 2.a. Extra Work 1,201,375.08 683.11 b. Adjustment Comp. -24,355.92 0.00 3. Materials on Hand 4. Earned Subject to Retention 16,400,327.08 51,522.82 5. Mobilization 919,254.00 0.00 6. Total Work Completed 17,319,581.08 7. Deductions -26,723.07 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,292,858.01 50,522.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 50,522.82