Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-09-18 02-387304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 100% 02-SHA-5-58.0/67.0 Federal Project: ACIM-005-8(325) ACIM-005-8(325) Progress payment No. 18 Payment period ending: 06-20-08 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,241,429.71 0.00 2.a. Extra Work 2,789,223.54 1,541,211.67 b. Adjustment Comp. -24,355.92 0.00 3. Materials on Hand 4. Earned Subject to Retention 18,006,297.33 1,541,211.67 5. Mobilization 919,254.00 0.00 6. Total Work Completed 18,925,551.33 7. Deductions -26,723.07 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,898,828.26 1,541,211.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,541,211.67