Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-017-15-15 02-390004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-TRI-299-60.8/61.2 Federal Project: NONE Progress payment No. 06 Payment period ending: 11-20-07 R BROWN CONSTRUCTION COMPANY INC P O BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 867,341.56 5,548.75 2.a. Extra Work 114,987.37 4,692.89 b. Adjustment Comp. 6,167.74 -682.26 3. Materials on Hand 4. Earned Subject to Retention 988,496.67 9,559.38 5. Mobilization 6. Total Work Completed 988,496.67 7. Deductions 8. a.Contract Retentions -48,946.86 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 48,946.86 48,946.86 9. Total pay to Contractor 988,496.67 58,506.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,506.24