Dept. of Trans. PROGRESS Serial No. Contract No. 10-021-09-29 02-395804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 22% 02-SHA-5-R43.1/ .0 Federal Project: ACSH-058(338) NH-058(338) Progress payment No. 02 Payment period ending: 01-20-10 GIFFORD CONSTRUCTION INC P O BOX 492618 REDDING CA 960492618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 189,327.44 87,733.93 2.a. Extra Work b. Adjustment Comp. 4,933.60 4,933.60 3. Materials on Hand 4. Earned Subject to Retention 194,261.04 92,667.53 5. Mobilization 6. Total Work Completed 194,261.04 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 194,261.04 92,667.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 92,667.53