Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-182-12-51 02-398404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SHA-273-14.4/ .0 Federal Project: NONE Progress payment No. 07 Payment period ending: 05-25-06 RON HALE CONSTRUCTION INC P O BOX 795 SHASTA LAKE CA 96019 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 231,206.68 3,000.00 2.a. Extra Work 34,275.87 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 265,482.55 3,000.00 5. Mobilization 6. Total Work Completed 265,482.55 7. Deductions 0.00 20,000.00 8. a.Contract Retentions -12,752.88 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 12,752.88 0.00 9. Total pay to Contractor 265,482.55 23,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,000.00