Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 09-286-13-16 02-3C0804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 26% 46% 02-TRI-299-13.3/13.8 Federal Project: ACHS-P299(155) NH-P299(155) Progress payment No. 04 Payment period ending: 09-17-09 R BROWN CONSTRUCTION COMPANY INC P O BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 542,641.55 0.00 2.a. Extra Work 67,847.05 6,242.44 b. Adjustment Comp. 160,500.00 160,500.00 3. Materials on Hand 26,870.56 26,870.56 4. Earned Subject to Retention 797,859.16 193,613.00 5. Mobilization 174,800.00 36,800.00 6. Total Work Completed 945,788.60 7. Deductions -11,000.00 1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 961,659.16 231,413.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 231,413.00