Dept. of Trans. PROGRESS Serial No. Contract No. 11-313-09-07 02-3C0804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 99% 02-TRI-299-13.3/13.8 Federal Project: ACHS-P299(155) NH-P299(155) Progress payment No. 26 Payment period ending: 10-20-11 R BROWN CONSTRUCTION COMPANY INC P O BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,463,633.70 0.00 2.a. Extra Work 2,118,944.70 39,116.29 b. Adjustment Comp. 265,642.66 -4,240.51 3. Materials on Hand 4. Earned Subject to Retention 4,848,221.06 34,875.78 5. Mobilization 184,000.00 0.00 6. Total Work Completed 5,032,221.06 7. Deductions -2,466.20 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,029,754.86 34,875.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,875.78