Dept. of Trans. PROGRESS Serial No. Contract No. 07-204-14-13 02-3C1414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 47% 02-SHA-5-R28.0/R29.0 Federal Project: NONE Progress payment No. 14 Payment period ending: 07-20-07 GOLDEN STATE BRIDGE INC 901 HOWE ROAD MARTINEZ CA 94553 Escrow No. 02247 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,568,452.50 801,876.65 2.a. Extra Work 871,854.97 49,050.71 b. Adjustment Comp. 27,553.70 0.00 3. Materials on Hand 173,705.07 0.00 4. Earned Subject to Retention 8,641,566.24 850,927.36 5. Mobilization 1,610,000.00 80,500.00 6. Total Work Completed 10,077,861.17 7. Deductions 8. a.Contract Retentions -432,078.31 -42,546.37 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,819,487.93 888,880.99 10. Reduction Amt to Escrow 11. Payment to Escrow 432,070.00 12. Net Pymt. this Estimate 888,880.99