Dept. of Trans. PROGRESS Serial No. Contract No. 08-021-13-05 02-3C1414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 67% 72% 02-SHA-5-R28.0/R29.0 Federal Project: NONE Progress payment No. 21 Payment period ending: 01-18-08 GOLDEN STATE BRIDGE INC 901 HOWE ROAD MARTINEZ CA 94553 Escrow No. 02247 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,586,099.95 599,430.65 2.a. Extra Work 2,027,844.79 91,284.78 b. Adjustment Comp. 43,471.80 8,929.70 3. Materials on Hand 543,185.09 439,922.74 4. Earned Subject to Retention 14,200,601.63 1,139,567.87 5. Mobilization 1,610,000.00 0.00 6. Total Work Completed 15,267,416.54 7. Deductions 8. a.Contract Retentions -710,030.08 -56,978.39 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,100,571.55 1,082,589.48 10. Reduction Amt to Escrow 11. Payment to Escrow 710,030.00 12. Net Pymt. this Estimate 1,082,589.48