Dept. of Trans. PROGRESS Serial No. Contract No. 08-109-13-23 02-3C1414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 80% 02-SHA-5-R28.0/R29.0 Federal Project: NONE Progress payment No. 24 Payment period ending: 04-18-08 GOLDEN STATE BRIDGE INC 901 HOWE ROAD MARTINEZ CA 94553 Escrow No. 02247 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,607,754.93 333,922.55 2.a. Extra Work 2,389,466.55 326,878.33 b. Adjustment Comp. 43,471.80 0.00 3. Materials on Hand 250,373.23 13,636.63 4. Earned Subject to Retention 16,291,066.51 674,437.51 5. Mobilization 1,610,000.00 0.00 6. Total Work Completed 17,650,693.28 7. Deductions 8. a.Contract Retentions -814,553.33 -33,721.88 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,086,513.18 640,715.63 10. Reduction Amt to Escrow 11. Payment to Escrow 814,550.00 12. Net Pymt. this Estimate 640,715.63