Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-10-32 02-3C2904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 64% 02-TEH-36-L41.0/ .0 Federal Project: NONE Progress payment No. 05 Payment period ending: 06-20-08 RICHARD A HEAPS ELECTRICAL CONTRACTOR INC 8909 FLORIN ROAD SACRAMENTO CA 95829 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 239,698.50 21,034.80 2.a. Extra Work 743.00 743.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 240,441.50 21,777.80 5. Mobilization 6. Total Work Completed 240,441.50 7. Deductions 8. a.Contract Retentions -12,022.08 -1,088.89 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 228,419.42 20,688.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,688.91