Dept. of Trans. PROGRESS Serial No. Contract No. 13-113-12-55 02-3C3004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 12% 02-PLU-70-0.1/35.1 Federal Project: ACHS-P070(102) STP Progress payment No. 08 Payment period ending: 04-18-13 STEWART ENGINEER INC PO BOX 990010 REDDING, CA 96099 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,654,160.82 466,426.96 2.a. Extra Work 50,188.69 7,994.38 b. Adjustment Comp. 10,565.10 1,083.60 3. Materials on Hand 106,926.06 -82,988.69 4. Earned Subject to Retention 2,821,840.67 392,516.25 5. Mobilization 570,000.00 0.00 6. Total Work Completed 3,284,914.61 7. Deductions 0.00 9,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,391,840.67 401,516.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 401,516.25