Dept. of Trans. PROGRESS Serial No. Contract No. 08-234-10-06 02-3C8704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 85% 02-SIS-3-8.7/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 08-20-08 BLAISDELL CONSTRUCTION INC P O BOX 493459 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 639,993.20 231,179.94 2.a. Extra Work 90,152.40 25,575.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 730,145.60 256,754.94 5. Mobilization 100,000.00 5,000.00 6. Total Work Completed 830,145.60 7. Deductions 0.00 2,000.00 8. a.Contract Retentions -36,507.28 -12,837.75 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 793,638.32 250,917.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 250,917.19