Dept. of Trans. PROGRESS Serial No. Contract No. 16-147-08-12 02-3E4104 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 36% Location: Federal Project: 02-SHA-299-0.3/7.1 NHP-P299(185) Progress payment No. 016 Payment period ending: 05-20-16 STEVE MANNING CONSTRUCTION INC PO BOX 491660 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,927,832.52 2,744,003.55 2. a. Extra Work 672,899.48 12,469.54 b. Adustment Comp. 3. Materials on Hand 197,914.98 0.00 4. Earned Subject to Retention 19,798,646.98 2,756,473.09 5. Mobilization 1,800,000.00 0.00 6. Total Work Completed 21,400,732.00 7. Deductions -276,399.60 -55,975.79 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,322,247.38 2,700,497.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,700,497.30