Dept. of Trans. PROGRESS Serial No. Contract No. 16-251-11-20 02-3E4104 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 46% Location: Federal Project: 02-SHA-299-0.3/7.1 NHP-P299(185) Progress payment No. 020 Payment period ending: 08-20-16 STEVE MANNING CONSTRUCTION INC PO BOX 491660 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,431,721.01 1,192,500.00 2. a. Extra Work 983,960.02 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -121,646.00 4. Earned Subject to Retention 25,415,681.03 1,070,854.00 5. Mobilization 1,800,000.00 0.00 6. Total Work Completed 27,215,681.03 7. Deductions -22,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,193,681.03 1,070,854.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,070,854.00