Dept. of Trans. PROGRESS Serial No. Contract No. 12-282-11-10 02-3E7504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 44% 02-SIS-5-19.0/25.3 Federal Project: IM00-5916(9E) Progress payment No. 08 Payment period ending: 09-17-12 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,630,747.55 1,901,743.45 2.a. Extra Work 130,236.04 11,550.00 b. Adjustment Comp. -33,710.25 0.00 3. Materials on Hand 185,020.84 0.00 4. Earned Subject to Retention 7,912,294.18 1,913,293.45 5. Mobilization 712,500.00 0.00 6. Total Work Completed 8,439,773.34 7. Deductions -15,000.00 -15,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,609,794.18 1,898,293.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,898,293.45