Dept. of Trans. PROGRESS Serial No. Contract No. 12-297-10-34 02-3E7504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 54% 02-SIS-5-19.0/25.3 Federal Project: IM00-5916(9E) Progress payment No. 09 Payment period ending: 10-18-12 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,871,053.88 2,240,306.33 2.a. Extra Work 130,236.04 0.00 b. Adjustment Comp. -33,710.25 0.00 3. Materials on Hand 185,020.84 0.00 4. Earned Subject to Retention 10,152,600.51 2,240,306.33 5. Mobilization 750,000.00 37,500.00 6. Total Work Completed 10,717,579.67 7. Deductions -19,000.00 -4,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,883,600.51 2,273,806.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,273,806.33