Dept. of Trans. PROGRESS Serial No. Contract No. 13-113-13-51 02-3E7604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 39% 02-SIS-5-51.2/58.1 Federal Project: ACIM-059(170) Progress payment No. 12 Payment period ending: 04-18-13 ROAD AND HIGHWAY BUILDERS OF CALIFORNIA INC P O BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,655,687.55 608,792.90 2.a. Extra Work 63,906.53 0.00 b. Adjustment Comp. -34,246.44 0.00 3. Materials on Hand 247,835.80 2,460.25 4. Earned Subject to Retention 6,933,183.44 611,253.15 5. Mobilization 3,285,900.75 0.00 6. Total Work Completed 9,971,248.39 7. Deductions -26,000.00 14,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,193,084.19 625,253.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 625,253.15