Dept. of Trans. PROGRESS Serial No. Contract No. 13-142-15-07 02-3E7604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 27% 44% 02-SIS-5-51.2/58.1 Federal Project: ACIM-059(170) Progress payment No. 13 Payment period ending: 05-20-13 ROAD AND HIGHWAY BUILDERS OF CALIFORNIA INC P O BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,089,267.55 1,433,580.00 2.a. Extra Work 63,906.53 0.00 b. Adjustment Comp. -34,246.44 0.00 3. Materials on Hand 558,091.96 310,256.16 4. Earned Subject to Retention 8,677,019.60 1,743,836.16 5. Mobilization 4,162,140.95 876,240.20 6. Total Work Completed 12,281,068.59 7. Deductions -30,000.00 -4,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,809,160.55 2,616,076.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,616,076.36