Dept. of Trans. PROGRESS Serial No. Contract No. 13-200-13-03 02-3E7604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 43% 54% 02-SIS-5-51.2/58.1 Federal Project: ACIM-059(170) Progress payment No. 16 Payment period ending: 07-18-13 ROAD AND HIGHWAY BUILDERS OF CALIFORNIA INC P O BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,555,786.17 3,544,719.50 2.a. Extra Work 63,906.53 0.00 b. Adjustment Comp. -33,206.44 0.00 3. Materials on Hand 133,121.39 74,052.00 4. Earned Subject to Retention 15,719,607.65 3,618,771.50 5. Mobilization 4,162,140.95 0.00 6. Total Work Completed 19,748,627.21 7. Deductions -28,000.00 2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,853,748.60 3,620,771.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,620,771.50