Dept. of Trans. PROGRESS Serial No. Contract No. 13-263-11-52 02-3E7604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 66% 02-SIS-5-51.2/58.1 Federal Project: ACIM-059(170) Progress payment No. 18 Payment period ending: 09-17-13 ROAD AND HIGHWAY BUILDERS OF CALIFORNIA INC P O BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,234,326.52 1,384,754.55 2.a. Extra Work 67,729.48 1,372.95 b. Adjustment Comp. -59,206.44 -26,000.00 3. Materials on Hand 300,311.13 183,624.46 4. Earned Subject to Retention 19,543,160.69 1,543,751.96 5. Mobilization 4,162,140.95 0.00 6. Total Work Completed 23,404,990.51 7. Deductions -38,000.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,667,301.64 1,541,751.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,541,751.96