Dept. of Trans. PROGRESS Serial No. Contract No. 13-294-16-19 02-3E7604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 72% 02-SIS-5-51.2/58.1 Federal Project: ACIM-059(170) Progress payment No. 19 Payment period ending: 10-17-13 ROAD AND HIGHWAY BUILDERS OF CALIFORNIA INC P O BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,069,306.80 3,834,980.28 2.a. Extra Work 212,758.76 145,029.28 b. Adjustment Comp. -59,206.44 0.00 3. Materials on Hand 211,387.67 -88,923.46 4. Earned Subject to Retention 23,434,246.79 3,891,086.10 5. Mobilization 4,381,201.00 219,060.05 6. Total Work Completed 27,604,060.12 7. Deductions -48,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,767,447.79 4,100,146.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,100,146.15