Dept. of Trans. PROGRESS Serial No. Contract No. 14-080-07-59 02-3E7604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 76% 02-SIS-5-51.2/58.1 Federal Project: ACIM-059(170) Progress payment No. 21 Payment period ending: 03-20-14 ROAD AND HIGHWAY BUILDERS OF CALIFORNIA INC P O BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,977,273.50 121,125.00 2.a. Extra Work 431,142.27 26,141.90 b. Adjustment Comp. -59,206.44 0.00 3. Materials on Hand 249,266.70 102,077.03 4. Earned Subject to Retention 24,598,476.03 249,343.93 5. Mobilization 4,381,201.00 0.00 6. Total Work Completed 28,730,410.33 7. Deductions -80,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 28,899,677.03 249,343.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 249,343.93