Dept. of Trans. PROGRESS Serial No. Contract No. 14-169-11-23 02-3E7604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 87% 02-SIS-5-51.2/58.1 Federal Project: ACIM-059(170) Progress payment No. 23 Payment period ending: 06-16-14 ROAD AND HIGHWAY BUILDERS OF CALIFORNIA INC P O BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,998,832.10 3,505,791.05 2.a. Extra Work 542,474.87 69,947.49 b. Adjustment Comp. -9,431.44 49,775.00 3. Materials on Hand 228,210.00 114,105.00 4. Earned Subject to Retention 28,760,085.53 3,739,618.54 5. Mobilization 4,381,201.00 0.00 6. Total Work Completed 32,913,076.53 7. Deductions -917,000.00 -837,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. -373,961.85 -373,961.85 c. Reduction after 95% Comp. 9. Total pay to Contractor 31,850,324.68 2,528,656.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,528,656.69