Dept. of Trans. PROGRESS Serial No. Contract No. 14-324-15-10 02-3E7604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 100% 02-SIS-5-51.2/58.1 Federal Project: ACIM-059(170) Progress payment No. 28 Payment period ending: 11-18-14 ROAD AND HIGHWAY BUILDERS OF CALIFORNIA INC P O BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 38,749,349.20 709,436.30 2.a. Extra Work 630,538.28 77,074.06 b. Adjustment Comp. -10,308.69 -877.25 3. Materials on Hand 4. Earned Subject to Retention 39,369,578.79 785,633.11 5. Mobilization 4,381,201.00 0.00 6. Total Work Completed 43,750,779.79 7. Deductions -597,888.86 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 43,152,890.93 775,633.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 775,633.11