Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-018-09-45 02-3E7714 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-TRI-299-36.9/53.5 STP-P299(189) Progress payment No. 023 Payment period ending: 11-09-17 MERCER FRASER COMPANY PO BOX 1006 EUREKA CA 955021006 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,633,774.14 60,137.50 2. a. Extra Work 527,298.48 141,439.10 b. Adustment Comp. 223,767.79 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,384,840.41 201,576.60 5. Mobilization 740,000.00 0.00 6. Total Work Completed 10,124,840.41 7. Deductions -106,187.50 -96,187.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,018,652.91 105,389.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 105,389.10