Dept. of Trans. PROGRESS Serial No. Contract No. 15-111-15-12 02-3E7904 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 7% Location: Federal Project: 02-TRI-299-12.3/12.9 HSNH-P299(182) Progress payment No. 003 Payment period ending: 04-20-15 J.F. SHEA CONSTRUCTION, INC. P. O. BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 75,650.00 41,600.00 2. a. Extra Work 18,583.93 10,771.47 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 94,233.93 52,371.47 5. Mobilization 6. Total Work Completed 94,233.93 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 94,233.93 52,371.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,371.47