Dept. of Trans. PROGRESS Serial No. Contract No. 16-081-11-38 02-3E7904 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 75% Location: Federal Project: 02-TRI-299-12.3/12.9 HSNH-P299(182) Progress payment No. 014 Payment period ending: 03-20-16 J.F. SHEA CONSTRUCTION INC. PO BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,653,206.78 58,730.00 2. a. Extra Work 283,840.01 66,263.40 b. Adustment Comp. 30,891.25 17,671.25 3. Materials on Hand 93,991.91 0.00 4. Earned Subject to Retention 4,061,929.95 142,664.65 5. Mobilization 267,000.00 0.00 6. Total Work Completed 4,234,938.04 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,328,929.95 142,664.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 142,664.65