Dept. of Trans. PROGRESS Serial No. Contract No. 12-263-13-32 02-3E8804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 60% 02-VAR Federal Project: NONE Progress payment No. 01 Payment period ending: 09-17-12 DIG IT CONSTRUCTION INC P O BOX 494 CHESTER CA 96020 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 991,469.62 991,469.62 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 991,469.62 991,469.62 5. Mobilization 6. Total Work Completed 991,469.62 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 991,469.62 991,469.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 991,469.62