Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-303-15-42 02-3E9904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SHA-44-1.7/4.3 Federal Project: NONE Progress payment No. 04 Payment period ending: 10-02-12 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,206,171.00 0.00 2.a. Extra Work 22,724.50 9,350.00 b. Adjustment Comp. -2,500.00 -2,500.00 3. Materials on Hand 4. Earned Subject to Retention 3,226,395.50 6,850.00 5. Mobilization 6. Total Work Completed 3,226,395.50 7. Deductions -46,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,180,395.50 6,850.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,850.00