Dept. of Trans. PROGRESS Serial No. Contract No. 23-362-12-05 02-3H32U4 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 24% Location: Federal Project: 02-SIS-5-2.5/R15.9 ACNH-059(181) Progress payment No. 007 Payment period ending: 12-20-23 WALSH-MYERS JOINT VENTURE 929 W ADAMS ST CHICAGO IL 60607 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 36,152,601.41 1,733,055.80 2. a. Extra Work 57,956.15 0.00 b. Adustment Comp. -206,173.36 -206,173.36 3. Materials on Hand 4. Earned Subject to Retention 36,004,384.20 1,526,882.44 5. Mobilization 12,489,503.95 0.00 6. Total Work Completed 48,493,888.15 7. Deductions -83,376.22 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 48,410,511.93 1,526,882.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,526,882.44