Dept. of Trans. PROGRESS Serial No. Contract No. 24-023-08-58 02-3H32U4 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 25% Location: Federal Project: 02-SIS-5-2.5/R15.9 ACNH-059(181) Progress payment No. 008 Payment period ending: 01-20-24 WALSH-MYERS JOINT VENTURE 929 W ADAMS ST CHICAGO IL 60607 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 36,725,859.92 573,258.52 2. a. Extra Work 57,956.15 0.00 b. Adustment Comp. -206,173.36 0.00 3. Materials on Hand 4. Earned Subject to Retention 36,577,642.71 573,258.52 5. Mobilization 12,489,503.95 0.00 6. Total Work Completed 49,067,146.66 7. Deductions -83,376.22 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 48,983,770.44 573,258.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 573,258.52