Dept. of Trans. PROGRESS Serial No. Contract No. 24-144-14-48 02-3H32U4 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 35% Location: Federal Project: 02-SIS-5-2.5/R15.9 ACNH-059(181) Progress payment No. 012 Payment period ending: 05-20-24 WALSH-MYERS JOINT VENTURE 929 W ADAMS ST CHICAGO IL 60607 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 57,164,158.50 14,030,633.18 2. a. Extra Work 639,662.25 0.00 b. Adustment Comp. -206,173.36 0.00 3. Materials on Hand 1,718,598.12 0.00 4. Earned Subject to Retention 59,316,245.51 14,030,633.18 5. Mobilization 12,489,503.95 0.00 6. Total Work Completed 70,087,151.34 7. Deductions -86,376.22 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 71,719,373.24 14,020,633.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,020,633.18