Dept. of Trans. PROGRESS Serial No. Contract No. 24-172-08-49 02-3H32U4 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 47% Location: Federal Project: 02-SIS-5-2.5/R15.9 ACNH-059(181) Progress payment No. 013 Payment period ending: 06-20-24 WALSH-MYERS JOINT VENTURE 929 W ADAMS ST CHICAGO IL 60607 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 71,806,938.52 14,642,780.03 2. a. Extra Work 660,509.33 20,847.08 b. Adustment Comp. -206,173.36 0.00 3. Materials on Hand 1,648,522.36 -70,075.76 4. Earned Subject to Retention 73,909,796.85 14,593,551.35 5. Mobilization 13,146,846.26 657,342.31 6. Total Work Completed 85,408,120.75 7. Deductions -76,376.22 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 86,980,266.89 15,260,893.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,260,893.66