Dept. of Trans. PROGRESS Serial No. Contract No. 24-239-09-26 02-3H32U4 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 56% Location: Federal Project: 02-SIS-5-2.5/R15.9 ACNH-059(181) Progress payment No. 015 Payment period ending: 08-20-24 WALSH-MYERS JOINT VENTURE 929 W ADAMS ST CHICAGO IL 60607 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 89,027,463.77 7,048,588.80 2. a. Extra Work 1,766,083.46 0.00 b. Adustment Comp. 256,946.64 463,120.00 3. Materials on Hand 1,666,288.54 17,766.18 4. Earned Subject to Retention 92,716,782.41 7,529,474.98 5. Mobilization 13,146,846.26 0.00 6. Total Work Completed 104,197,340.13 7. Deductions -103,376.22 -17,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 105,760,252.45 7,512,474.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,512,474.98