Dept. of Trans. PROGRESS Serial No. Contract No. 24-298-12-47 02-3H32U4 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 65% Location: Federal Project: 02-SIS-5-2.5/R15.9 ACNH-059(181) Progress payment No. 017 Payment period ending: 10-20-24 WALSH-MYERS JOINT VENTURE 929 W ADAMS ST CHICAGO IL 60607 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 111,929,372.07 6,565,356.57 2. a. Extra Work 1,808,930.35 42,846.89 b. Adustment Comp. -438,147.96 -695,094.60 3. Materials on Hand 0.00 -39,543.08 4. Earned Subject to Retention 113,300,154.46 5,873,565.78 5. Mobilization 13,146,846.26 0.00 6. Total Work Completed 126,447,000.72 7. Deductions -53,376.22 40,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 126,393,624.50 5,913,565.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,913,565.78