Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 24-309-10-10 02-3H32U4 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 65% Location: Federal Project: 02-SIS-5-2.5/R15.9 ACNH-059(181) Progress payment No. 018 Payment period ending: 10-20-24 WALSH-MYERS JOINT VENTURE 929 W ADAMS ST CHICAGO IL 60607 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 115,879,100.80 3,949,728.73 2. a. Extra Work 1,808,930.35 0.00 b. Adustment Comp. -438,147.96 0.00 3. Materials on Hand 4. Earned Subject to Retention 117,249,883.19 3,949,728.73 5. Mobilization 13,146,846.26 0.00 6. Total Work Completed 130,396,729.45 7. Deductions -53,376.22 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 130,343,353.23 3,949,728.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,949,728.73